Street Resurfacing Program

Print

Resurfacing

Annually, Engineering evaluates the surface condition of all City maintained streets to identify and prioritize roads that need maintenance. In addition, the street resurfacing program must also be kept within the constraints of the City’s established budget for this program.

Once a fiscally responsible program has been developed, the program is put out for competitive bid. The program is usually developed over the winter, with bidding in the early spring and construction occurring in early to midsummer.

Once a road has been resurfaced, the surface is expected to have a life of about twenty years. However, there are several variables that can affect the life expectancy of a road, including amount of traffic that drives on it, the type of soil beneath the road, and weather conditions.

Project Contact: Jason MacNally, Engineering and Building Inspector
Cell Phone: (815) 790-6948
Email: jmacnally@crystallake.org

2016 Street Resurfacing Program: 

  • October 5, 2016: The contractor will be working on the punch list items which include the removal and replacement of Oxford Lane due to the poor pavement placement.
  • September 28, 2016: The resurfacing program will be substantially complete on September 29.
  • September 21, 2016: Placement of the final layer of asphalt continues. The placement of pavement markings will start next week.  
  • September 14, 2016: All pavement removals are complete and the first layer of asphalt is complete on all roadways. Placement of the final layer of asphalt continues. The placement of pavement markings will start next week. The contractor is on schedule to have the program complete by the completion date of September 30.
  • September 7, 2016:  The contractor started removing pavement and paving in the Country Club area.
  • August 31, 2016: The pavement was removed and the first layer placed on Washington Street. The manhole lids were raised on Washington Street, King Street and Florence Street with the final paving scheduled for September 2. The contractor will start pavement removal in the Country Club area on September 1.
  • August 24: 2016:  The contractor will continue working on August 26.
  • August 17, 2016:  The contractor continues pavement milling and placing asphalt.
  • August 10, 2016: The contractor continues pavement milling and placing asphalt.
  • August 3, 2016: The contractor started pavement milling and placing of the first layer of asphalt. Work will continue with pavement removal and asphalt placement.
  • July 29, 2016: The contractor started pavement removal along the streets west of the Lake. Pavement removal will continue and placement of asphalt will also start. 
  • July 20, 2016: The contractor lowered all the manhole frames and lids so the pavement could be removed. Pavement removal is expected to start in the next few weeks.
  • June 29, 2016:  The contractor plans to be onsite next week. They will be starting on roadways in the area west of the lake. This project will not be affected by the lack of a state budget. 
  • June 22, 2016:  The contractor may be onsite next week. They will be starting on roadways in the west end.
  • April 4, 2016: The City Council awarded the contract to Arrow Road. 
  • February 9,2016: Bids were opened for the 2016 Street Resurfacing Program. The low bidder was Arrow Road. (Bid Tab)
 2016 Street Resurfacing Program

Amberwood Drive

Golf Course Road

Bennington Drive

Ballard Road Briarwood Road Pauline Avenue
Bennington Drive Augusta Drive Amberwood Drive
Briarwood Circle Briarwood Road Butternut Drive
Broadway Avenue (eastbound lane) Country Club Road Meridian Street
Butternut Drive West City Limits Briarwood Road
Concord Drive Windslow Drive High School Access Road
Country Club Road Lake Avenue Wedgewood Drive
Cumberland Lane Country Club Road Broadway Avenue
Essex Lane Country Club Road Broadway Avenue
Florence Street Virginia Street Pierson Street
Goldenrod Court Wedgewood Drive end
Heather Drive Gardina Lane Mulberry Lane
Heather Drive Butternut Drive Bunker Lane
Iris Court Wedgewood Drive end
King Street Virginia Street Pierson Street
Lake Avenue Country Club Road City Limits
Lake Court Leonard Parkway End
Lakeside Avenue Country Club Road Broadway Avenue
Lakeview Drive Wedgewood Drive Huntley Road
Leonard Parkway Lake Shore Drive End
Melrose Lane Country Club Road Broadway Avenue
Meridian Street Country Club Road Broadway Avenue
Monterey Drive Brentwood Drive McHenry Avenue
Oriole Trail Crystal Lake Avenue Rockland Drive
Oxford Lane Country Club Road Broadway Avenue
Park Lane Leonard Parkway End
Riverside Drive East Country Club Road Lake Avenue
Riverside Drive West Country Club Road Broadway Avenue
Washington Street Virginia Street Lake Street
Wedgewood Drive Boneset Dr Eastern Court
Windsor Drive Dartmoor Drive Golf Course Road
Woodmar Drive Cress Creek Lane Monterey Drive
Woodland Drive End End

 

 

Location map